Hong Kong Airport — Fixed Link Bridges
Hong Kong
The Three Runway System is one of the largest infrastructure undertakings in Hong Kong International Airport’s history. REDD BIM’s involvement began with the Integrated Airport Centre steel roof, delivered as the pilot project for the expansion. Its success shaped the BIM approach and deliverables the Airport Authority went on to adopt across the wider program.
On the strength of that work, REDD was engaged to deliver design development and 3D steel modelling for 28 fixed link bridges connecting key parts of the expanded airport. The models were completed for the client ahead of builder contract award, so fabrication could commence immediately on award, with contractor queries and incomplete design documentation removed before they could affect the program.
Year: Completed August 2020
Client: Airport Authority Hong Kong
Location: Hong Kong International Airport
Sector: Aviation Infrastructure
Scale: ~5,000 tonnes across 28 fixed link bridges